Steps for Completing Alternative Sewage Disposal System Maintenance Schedule (ASDSMS) for Construction Authorization Completion:

ASDSMS are required to be recorded at the Wake County Register of Deeds for properties that require the use of an alternative or innovative wastewater system for wastewater disposal that requires the system to be operated by a certified subsurface wastewater operator for the life of the system.

  1. Print and fill out completely correct version of schedule:
    All documents are on 8 inch by 14 inch legal paper and must be submitted to Register of Deeds as such.
    1. Alternative sewage disposal system maintenance schedule: Pressure manifold
    2. Alternative sewage disposal system maintenance schedule: Pressure manifold with pretreatment
    3. Alternative sewage disposal system maintenance schedule: Pressure manifold with alternate fields
    4. Alternative sewage disposal system maintenance schedule: Low pressure pipe
    5. Alternative sewage disposal system maintenance schedule: Low pressure pipe with pretreatment
    6. Alternative sewage disposal system maintenance schedule: Drip irrigation with pretreatment
    7. Alternative sewage disposal system maintenance schedule: Drip irrigation with pretreatment (Grade II operators license required)
    8. Alternative sewage disposal system maintenance schedule: Warranty Systems
    9. Alternative sewage disposal system maintenance schedule: Disposal System utilizing Off-Site Easement
    10. Alternative sewage disposal system maintenance schedule: Repair Disposal System Only utilizing Off-Site Easement
  2. Have original paperwork notarized.
  3. Submit original paperwork to Wake County Register of Deeds.  See website for fees, contacts and directions.
  4. Send email to Wastewater Management Staff with Book and Page number the ASDSMS document was recorded.