​Stormwater Process:


The Stormwater Process in the Town of Zebulon is composed of the following: Preliminary Discussion, Initial Submission, Technical Review Committee, Construction Plan Review, Plan Approval, Permit Issuance, Permit Issuance, Permit Completion and Post-Construction Maintenance. In addition, Wake County administers the Town’s erosion and sediment control and stormwater regulations including related plan review and permit issuance.
 
 
 
Prior to initiating a stormwater application, the applicant should be familiar with Town of Zebulon Code of Ordinances, Chapter 152. All applicants must adhere to the Town of Zebulon's Comprehensive Plan and Transportation Plan in addition to the following submittal requirements:
 
 
 

I. Preliminary Discussion

All development proposals have the option of scheduling a presubmittal meeting with the Town of Zebulon before any plan submittal process is initiated. Wake County staff will provide guidance on E&SC and stormwater submittals and site plan design guidance, in coordination with the Town of Zebulon. Applicants should call 919-269-7455 to schedule a meeting with the Town of Zebulon. See Town of Zebulon's fee schedule for any associated fees. Applicants should also email Watershed Manager Debbie Ryals (Debra.Ryals@wakegov.com) prior to this meeting and provide the following information:
 
  • Project Name 
  • Contact Information 
  • PIN Number 
  • Approximate Disturbed Acreage (if available) 
  • Summary of proposed development 
  • Sketch Plan (if available)
 

II. Initial Submission

Applicant must provide a site plan to be reviewed by the Technical Review Committee (TRC) and all plans should be submitted to the Town of Zebulon for distribution. See Town of Zebulon Code of Ordinances, Chapter 152. The site plan submittal for stormwater should include the following:
 
  • Cover letter stating the purpose of the submission 
  • Two (2) copies of the Municipal Stormwater Design Tool (Site Data Sheet, DA Sheets, Site Summary, and any other sheets available) 
  • Wake County Municipal Stormwater Submittal Checklist (Preliminary Plan portion) 
  • Wake County Municipal Standards Checklist 
  • Site Plan 
  • Drainage Area Map 
  • Copy of USGS Quad Map and Wake County Soil Survey map with delineated project limits 
  • Any additional calculations available
 
Wake County will provide review comments or plan approval directly to the Town of Zebulon for distribution prior to TRC. Applicant should adhere to the fee schedule for all resubmittals.
 
 
 

IV. Construction Plan Review

Following the TRC Review process, development and redevelopment with greater than 20,000 square feet of disturbance are required to obtain a Stormwater Permit through Wake County. Development with greater than 1 acre will have to obtain a Land Disturbance Permit through Wake County. The applicant shall submit the following to Wake County for stormwater construction plan review:
 
  • Cover letter stating the purpose of the submission 
  • Applicable fees 
  • Wake County Municipal Stormwater Submittal Checklist (Preliminary Plan and Construction Plan portion) 
  • Wake County Municipal Standards Checklist 
  • Two (2) copies of the Municipal Stormwater Design Tool (All sheets)
  • Five (5) copies of a complete set of construction drawings 
  • Drainage Area Map 
  • Copy of USGS Quad map and Wake County Soil Survey with delineated project limits 
  • All supporting calculation documentation 
  • Erosion Control requirements (applicant should submit a total of five (5) copies when submitting for both Stormwater and Erosion Control)
 

V. Permit Issuance

Following approval of construction drawings by Wake County and the Town of Zebulon, a pre-construction meeting with Wake County must be scheduled prior to any land disturbance. Applicant should contact Watershed Manager Debbie Ryals to schedule this meeting with Wake County. At this time, applicants will obtain the Stormwater Permit as well as a Land Disturbance Permit (if applicable). Additionally, applicant shall receive two copies of the approved stormwater and/or erosion control plan. Applicant should bring the following to the preconstruction meeting:
 
  • All associated permit fees 
  • Site contractor(s) 
  • Financially responsible party 
  • Engineer (if requested)
  •  
  

VI. Conditions of Approval

The following conditions of approval (as noted on construction plan stormwater approval letter) shall be provided to Wake County for review prior recordation of the final plat; Stormwater Agreement, Operation & Maintenance Plan, Engineer’s Certification, Asbuilt Survey, Covenants, Performance Guarantee, etc. See Town’s Town of Zebulon Code of Ordinances, Chapter 152 for additional information regarding as built drawings, final plat approval, and final plat recordation.
 
Rules Forms ​Staff Fees Interactive Map FAQs
 
 

Comments

 

Rollup Image

 
Approval Status Approved
 
Content Type: Article Page
Version: 7.0
Created at 8/8/2012 10:29 AM by Kathryn G. Hobby
Last modified at 2/4/2013 5:43 PM by Stephen R. Walston
FacebookTwitterE-newslettersFlickr