Review Schedules


Application Submittal Deadlines for Board of Adjustment Hearing/Review(s)

These submittal dates are applicable not only to Special Use Submittals, but for Zoning Hardship Variances, Appeals and Planned Compliance Permit Applications, as well.

 

Application Submittal Deadline

TRC Comments to Applicant 

Revised Application Deadline 

Board of Adjustment Meeting 

 1/3/2012

 2/10/2012

 2/24/2012

 4/10/2012

 2/7/2012

 3/9/2012

 3/23/2012

 5/8/2012

 3/6/2012

 4/13/2012

 4/27/2012

 6/12/2012

 4/3/2012

 5/11/2012

 5/25/2012

 7/10/2012

 5/1/2012

 6/15/2012

 6/29/2012

 8/14/2012

 6/5/2012

 7/13/2012

 7/27/2012

 9/11/2012

 7/3/2012

 8/10/2012

 8/24/2012

 10/9/2012

 8/7/2012

 9/14/2012

 9/28/2012

 11/13/2012

 9/4/2012

 10/12/2012

 10/26/2012

 12/11/2012

 10/2/2012

 11/9/2012

 11/23/2012

 1/8/2013

 11/6/2012

 12/14/2012

 12/28/2012

 2/12/2013

 12/4/2012

 1/11/2013

 1/25/2013

 3/12/2013

A complete petition must be delivered to the Zoning Administration office (Permits/Plans Review Center, Mall level, Wake County Office Building, 336 Fayetteville St., downtown Raleigh) by 2 p.m. Zoning Administration staff will review the petition for full compliance with all submittal requirements. If it does not fully comply, they will notify the petitioner of submittal deficiencies and allow him/her until 5 p.m. that day to correct the deficiencies and avoid deferral of the petition's review to a later review cycle.

Board meetings begin at 9 a.m. in Room 700 of the Wake County Courthouse, 316 Fayetteville St., downtown Raleigh. For more information about Special Use Permits and the petition review process, contact Brenda Coats: 919-856-6215; FAX: 919-856-5824, Wake County Zoning and Subdivision Administration, PO Box 550, Raleigh, NC 27602-0550.



Rezoning Petition Submittal Dates

 

Application Submittal Deadline

TRC Comments to Applicant 

Revised Application Deadline 

Planning Board Meeting 

 1/3/2012

 2/10/2012

 2/24/2012

 4/4/2012

 2/7/2012

 3/9/2012

 3/23/2012

 5/2/2012

 3/6/2012

 4/13/2012

 4/27/2012

 6/6/2012

 4/3/2012

 5/11/2012

 5/25/2012

 7/4/2012

 5/1/2012

 6/15/2012

 6/29/2012

 8/1/2012

 6/5/2012

 7/13/2012

 7/27/2012

 9/5/2012

 7/3/2012

 8/10/2012

 8/24/2012

 10/3/2012

 8/7/2012

 9/14/2012

 9/28/2012

 11/7/2012

 9/4/2012

 10/12/2012

 10/26/2012

 12/5/2012

 10/2/2012

 11/9/2012

 11/23/2012

 1/2/2013

 11/6/2012

 12/14/2012

 12/28/2012

 2/6/2013

 12/4/2012

 1/11/2013

 1/25/2013

 3/6/2013

A complete application must be delivered to the Planning office (Mall floor, Wake County Office Building, 336 Fayetteville St., downtown Raleigh) by 2 p.m. (appointments are encouraged). Planning staff will review the application for full compliance with all submittal requirements. If it does not fully comply, they will inform the applicant of submittal deficiencies and allow him/her until 5 p.m. that day to correct the deficiencies and avoid deferral of the application's review to a later review cycle.

Planning Board meetings begin at 1:30 p.m. in Room 700 of the Wake County Courthouse, 316 Fayetteville St., downtown Raleigh. Board of Commissioners meetings begin at 2 p.m. in Room 700 of the Wake County Courthouse, 316 Fayetteville St., downtown Raleigh.

For more information about the rezoning petition review process, contact Keith Lankford: 919-856-7569; FAX: 919-856-5824; Wake County Planning, PO Box 550, Raleigh, NC 27602-0550.

*Should a submittal date fall on day in which the County offices are closed, submittal will be allowed by 2 p.m. on the first available day.